Project Start Date: Tue 3/1/05
Project Finish Date: Fri 6/29/07
Name | Duration | Start_Date | Finish_Date |
---|---|---|---|
Walmart 6/29 (AS/KN) D | 104 days | Thu 2/1/07 | Fri 6/29/07 |
TOTAL PRODUCTION TIME | 104 days | Thu 2/1/07 | Fri 6/29/07 |
1) Tasks due by 6pm PST | 0 days | Thu 2/1/07 | Thu 2/1/07 |
2) Late delivery will impact launch | 0 days | Thu 2/1/07 | Thu 2/1/07 |
3) Schedule accomodates 3 rounds/revs only | 0 days | Thu 2/1/07 | Thu 2/1/07 |
Internal kick-off meeting w/sales: HANDOFF | 0 days | Mon 4/2/07 | Mon 4/2/07 |
Kick-off meeting w/client | 0 days | Tue 4/3/07 | Tue 4/3/07 |
CLIENT: All assets rec'd; PRODUCTION STARTS | 5 days | Tue 4/3/07 | Tue 4/10/07 |
DOL: Internal Production Kickoff | 1 day | Tue 4/10/07 | Wed 4/11/07 |
DOL: Wireframe or Concept Sketch | 3 days | Wed 4/11/07 | Mon 4/16/07 |
CLIENT: Approval | 4 days | Mon 4/16/07 | Fri 4/20/07 |
DOL: Comp 1 of 2: static comp for look/feel | 7 days | Fri 4/20/07 | Tue 5/1/07 |
CLIENT: Review | 4 days | Tue 5/1/07 | Mon 5/7/07 |
DOL: Comp 2 of 2: rev. static comp + 1 media | 7 days | Mon 5/7/07 | Wed 5/16/07 |
CLIENT: Review | 5 days | Wed 5/16/07 | Wed 5/23/07 |
DOL: Functional Site + All Media | 7 days | Wed 5/23/07 | Mon 6/4/07 |
Flash assets to Dev, media to Prod | 4 days | Wed 5/23/07 | Wed 5/30/07 |
Site development & posting | 3 days | Wed 5/30/07 | Mon 6/4/07 |
CLIENT: Review | 4 days | Mon 6/4/07 | Fri 6/8/07 |
DOL: Final Site + Final Media | 7 days | Fri 6/8/07 | Tue 6/19/07 |
Flash assets to Dev, media to Prod | 4 days | Fri 6/8/07 | Thu 6/14/07 |
Site development & posting | 2 days | Thu 6/14/07 | Mon 6/18/07 |
Legal & Editorial | 1 day | Mon 6/18/07 | Tue 6/19/07 |
CLIENT: Courtesy Review - no further changes please | 0 days | Tue 6/19/07 | Tue 6/19/07 |
DOL: Prep, Test & Soft Launch | 7 days | Tue 6/19/07 | Thu 6/28/07 |
Finalize & Prep site for QA | 1 day | Tue 6/19/07 | Wed 6/20/07 |
REVOPS: Setup & Deliver AdConfig | 2 days | Wed 6/20/07 | Fri 6/22/07 |
QA: Test of site w/adconfig | 4 days | Fri 6/22/07 | Thu 6/28/07 |
DOL: Soft launch of site (live test) | 1 day | Thu 6/28/07 | Fri 6/29/07 |
QA & ProdOps: Test media | 1 day | Thu 6/28/07 | Fri 6/29/07 |
Launch: (by 12:01am PST on IO date) | 0 days | Fri 6/29/07 | Fri 6/29/07 |
++Campaign Elements++ | 0 days | Fri 6/29/07 | Fri 6/29/07 |
PLEASE LIST OUT | 0 days | Fri 6/29/07 | Fri 6/29/07 |